Which Side Of Franklin Gets Road Relief First

The four-lane widening of Mack Hatcher Parkway on Franklin's southeast side is a $100 million project. On the City of Franklin's own project page, its construction start is listed as 2032. Work at the Del Rio Pike intersection on the northwest side is much smaller, about $1.75 million at the low bid, and the City's target for finishing it is 2027. The second project is a small fraction of the first, but it is the one that will change daily driving in this decade.

For anyone comparing parts of Franklin, that gap in timing should shape the comparison. Over the next several years, road relief in Franklin will arrive one intersection and one radial road at a time. Each part of town is waiting on a different item in the City's capital plan, and those items finish years apart.

Two quadrants of the parkway are still two lanes

The northwest piece of Mack Hatcher was built as a two-lane road with one bridge over the Harpeth River and a multiuse path, and it runs from Hillsboro Road to New Highway 96 West. Drivers get on at Del Rio Pike and Old Charlotte Pike. The western end lands near Westhaven, and the bridge crosses the river near Brownland Farm. The Williamson Herald, reporting ahead of the opening, described a second phase that would add a second bridge and widen the road to four lanes, and that phase had not been funded.

The southeast quadrant runs from SR-96 East to Columbia Avenue (US-31). It is also still two lanes. The City plans to rebuild it as a four-lane parkway with a median and a 12-foot multi-use trail.

How each quadrant gets paid for explains the timing. In a public letter to TDOT Commissioner Will Reid, State Representative Lee Reeves said Franklin had committed $50 million toward each of the two $100 million Mack Hatcher phases. The letter also said the City had already acquired the land and rights-of-way the work needs. The Williamson Herald quoted Reeves: "Franklin showed up to the potluck with the entrée, and right now they're still not being served." The Herald also reported that only the southeast segment was on TDOT's active list, and that the northwest segment was unfunded and not on the list.

The southeast segment's funding has grown since then. In May 2026, WKRN reported that the state added $15 million, raising TDOT's commitment from $25 million to $40 million. With Franklin's $50 million, that covers $90 million of a project expected to cost $100 million. TDOT's 10-Year Project Plan, last updated May 2, 2025, lists the southeast widening at $100.0 million with a construction year of 2032. The Williamson County rows of that plan include no entry for widening the northwest segment.

That leaves one quadrant with a construction year about six years away and another with no year at all. Neither will change a commute in the near term.

What Franklin is building in the meantime

The near-term changes are City projects at single intersections. They sit at the busiest points on both two-lane quadrants.

On the northwest, the Mack Hatcher Intersection Upgrades at Hillsboro & Del Rio add eastbound and westbound through lanes at Del Rio Pike and a westbound through lane at Hillsboro Road. The signal at Hillsboro will also be modified. The City describes the purpose as improving operations "pending full corridor widening." Construction was expected to start in 2026, with completion estimated in 2027. The City's bid tabulation dated October 1, 2026 lists four bids:

Bidder Bid
Jones Bros Contractors, LLC $1,746,966.00
Civil Constructors, LLC $1,912,019.10
Nickell Contracting, LLC $1,923,244.55
Grade A Construction, LLC $2,507,981.25

According to the tabulation, an award recommendation follows a period when the bid file stays open for review. At about $1.75 million, the lowest bid is less than 2 percent of the full southeast widening. On the west side, that small project is the one with a 2027 target date.

On the southeast quadrant, the Mack Hatcher & Royal Oaks Intersection Improvements add turn lanes on Mack Hatcher and on Royal Oaks Boulevard. The City says they are meant to handle peak-hour demand "until Mack Hatcher from SR-96 to US-31 is completed." The project page lists a 2026 construction start. Bids for the S. Royal Oaks Boulevard and Royal Oaks Court intersection were due May 15, 2026, under Invitation to Bid 2026-024. By the City's own description, this is a stopgap for the years before the 2032 widening.

The radial roads finish on their own schedules

Mack Hatcher works by connecting the roads that run out from downtown, and each of those roads has its own project with its own dates.

Columbia Avenue is the furthest along. It will become five lanes from Mack Hatcher to Downs Boulevard, with medians in some places and utilities moved into the roadway where possible. The estimated cost is $38 million. Up to $28.8 million is federal STBG money, up to $3.8 million comes from the state, and about $3.6 million is local. The City says it is acquiring land, rights-of-way and easements. City spending on the project stood at $2,744,441.79 as of November 14, 2026, and the page gives no construction start date. Columbia Avenue is also the western end of the southeast quadrant. When the corridor is finished, its south end will connect to a five-lane avenue, while Mack Hatcher at that same corner stays two lanes until 2032.

Boyd Mill Avenue is planned for widening from SR-96 to Downs Boulevard and may get sidewalks and bike facilities. The Board of Mayor and Aldermen has not yet set the final scope, and the estimated completion is 2030.

Franklin Road, north of Mack Hatcher toward Mallory Station Road, is in early planning. The City lists a tentative completion of 2032. A conceptual design and analysis contract with Gresham Smith is capped at $286,045.

The calendar, corridor by corridor

Here are the City's and TDOT's stated targets in one table, ordered by date. All dates are the agencies' own estimates.

Corridor Work Stated timing
Mack Hatcher at Hillsboro Rd and Del Rio Pike Added through lanes, signal change Start 2026, completion estimated 2027
Mack Hatcher at Royal Oaks Blvd Added turn lanes Construction start anticipated 2026
Columbia Ave, Mack Hatcher to Downs Blvd Five-lane widening, $38M estimate Right-of-way acquisition underway
Boyd Mill Ave, SR-96 to Downs Blvd Widening, scope to be set Completion estimated 2030
Franklin Rd, Mack Hatcher to Mallory Station Widening, early planning Tentative completion 2032
Mack Hatcher Southeast, SR-96 E to Columbia Ave Four-lane parkway, $100M estimate Construction estimated to begin 2032
Mack Hatcher Northwest, Hillsboro Rd to New Hwy 96 W Second bridge, four lanes Not in TDOT's 10-Year Plan table

Read top to bottom, the table shows the order in which changes arrive. The west side's main intersection fix comes first. The Columbia Avenue corridor is next in line because its right-of-way work has started. The southeast parkway and the Franklin Road corridor share a 2032 date. The northwest widening, the project that would give Westhaven-area traffic a four-lane route across the Harpeth, has no date.

Reading a Franklin address against this calendar

When a buyer is weighing a house off New Highway 96 West against one off Lewisburg Pike or Columbia Avenue, the route they will drive to Cool Springs or to I-65 matters as much as the house. The schedules above show which projects will change that route during the time most buyers expect to own the home.

An address that reaches Mack Hatcher at Del Rio Pike or Hillsboro Road depends mostly on the 2027 intersection work, because the full northwest widening has no state funding or schedule. An address that uses Mack Hatcher between SR-96 East and Columbia Avenue depends on the Royal Oaks turn lanes for now and on the 2032 parkway after that. An address that relies mainly on Columbia Avenue depends on a project already in right-of-way acquisition. When someone describes a commute as one that "will improve when Mack Hatcher is widened," it is fair to ask which quadrant they mean and what its stated year is.

Questions buyers ask about the Mack Hatcher work

Is the Mack Hatcher loop finished?

No. Ahead of the northwest opening, the Williamson Herald reported that TDOT and the City envisioned another leg in the southwest part of the city, connecting New Highway 96 and Columbia Avenue, to complete the loop. The northwest segment from Hillsboro Road to New Highway 96 West opened as two lanes with one Harpeth River bridge. The southeast segment from SR-96 East to Columbia Avenue is scheduled for widening, with construction estimated to begin in 2032.

Who is paying for the southeast widening?

As of WKRN's May 14, 2026 report, Franklin had committed $50 million and TDOT $40 million toward an expected $100 million cost.

Will the southeast widening include a trail?

Yes. The City's project description includes a 12-foot multi-use trail for bicycles and pedestrians.

If you are weighing Franklin addresses, or you own land along one of these corridors, the road calendar belongs in the decision. Greg Sanford Real Estate is glad to talk it through with you. Request a private consultation, or start with our Franklin real estate overview.