Spring Hill's New Homes Now Come From A Fixed List. Here's What's On It.

"Since then, two building permits have been issued," Spring Hill Mayor Matt Fitterer said at Franklin Tomorrow's Breakfast with the Mayors early this year, according to the Williamson Herald. He was describing the months after the city's sewer moratorium took effect. "We think we can be out from under it by 2030."

Most buyers compare Spring Hill to Thompson's Station or Columbia on price per square foot and drive time. For new construction, those comparisons now rank behind a bigger factor. The city allocated remaining sewer capacity to named projects and builders.

The friction appears before a contract does

The rule sits in Section 1 of Ordinance 25-29, which the Board of Mayor and Aldermen passed unanimously on second reading on January 5, 2026. It declares a sewer moratorium "prohibiting issuance of any new sewer capacity commitments, sewer availability letters, or sewer connection approvals, except as authorized through this Ordinance."

The ordinance says it was adopted to comply with TDEC Consent Order WPC2025-0093. It also aims to prevent allocating capacity beyond what the system can handle and to provide what it calls "a fair and predictable mechanism for distributing all remaining sewer capacity." Every project that receives an allocation must install flow meters, so the city can check that each project stays within its share.

The list, as adopted January 5, 2026

Section 2 sorts the remaining capacity into two groups. Group 1 covers projects with development agreements and received 207,403 gallons per day.

Group 1 project Allocation, gallons per day
Legacy Pointe 62,995
June Lake 58,000
Spring Hill Commerce Center 20,000
John Maher Builders 18,000
Belle Springs 12,600
Barton Hills 12,000
Spring Hill Towne Crossing 10,808
Goodall Homes 6,000
Patterson Company 6,000
Smyrna Ready Mix 1,000
Arbor Valley, multiple builders No figure shown

Group 2 covers permit-ready vacant lots and totals 250 units and 62,500 gallons per day.

Group 2 neighborhood or builder Units Gallons per day
Harvest Point, multiple builders Not shown 16,500
August Park, multiple builders Not shown 9,000
DR Horton 48 Not shown
Brandon Woods 39 9,750
Alaina Park 24 6,000
Hardins Landing 24 6,000
Bluebird Hollow 22 5,500
Toll Brothers 18 Not shown
Richmond American 18 Not shown
Mountain View 16 4,000
Crystal Creek 16 4,000
Celebration 14 Not shown
Regent Homes 4 Not shown
Maebry 4 1,000
Cherry Grove 3 750

The Group 2 rows that show both columns use the same conversion. Brandon Woods gets 9,750 gallons for 39 lots, Alaina Park 6,000 for 24, and Cherry Grove 750 for 3, which works out to 250 gallons a day per house.

The ordinance then states that the Group 1 and Group 2 allocations use up all remaining treatment capacity and that no additional development capacity is available.

Where the rest of the gallons went

Beyond the two groups, the same ordinance committed capacity in three other places.

  • 365,000 gallons per day to building permits already active on the ordinance's effective date
  • 65,000 gallons per day to a hospital on Reserve Boulevard and to city Public Works and Fleet buildings
  • A 100,000-gallon-per-day reserve that the Board may allocate for nonresidential tenant improvements in existing buildings, but only for properties outside Groups 1 and 2

That reserve is the only flexible capacity the ordinance created, and it doesn't serve housing. The January 5 agenda packet records a request for 845 gallons a day for two previously unoccupied spaces on Port Royal Road, and another for 187 gallons a day for tenant-space renovations at Vanderbilt-Ingram Cancer Center.

The city's own budget reflects this. When the Board passed its $151.7 million FY27 budget on June 15, 2026, one of the listed items was a "projected decrease in development fee revenue, due to sewer moratorium."

The Columbia pipe adds capacity later, not now

On October 19, 2026, the Board unanimously passed Resolution 26-302 to move ahead with an interlocal wastewater plan with the City of Columbia. Columbia's City Council had already voted in favor on October 8.

According to the city, the project is a 12-inch sewer main running from the Spring Hill Reclamation Plant on Mahlon Moore Road, along Mahlon Moore Road and then several miles of TVA easement, to Columbia's system at its northern city limits. Projected costs are about $12 million: $9 million for the pipeline and $3 million for upgrades to the Carter's Creek Pike Pump Station. Spring Hill pays for the project. Once it's complete, the main would carry at least 500,000 gallons a day and as much as 1.5 million, and Spring Hill would pay Columbia a usage rate.

At the 250-gallon figure from the Group 2 table, the 500,000-gallon minimum works out to about 2,000 houses. That is roughly eight times the permit-ready lots on the current list. The agreement makes conveyance conditional on written approval from TDEC, and Columbia's service begins only after its new treatment plant and the required pump-station work are finished. The Williamson Herald reported that the Columbia plant is under construction and expected to be finished in 2027, raising Columbia's treatment capacity to 17 million gallons a day.

The agreement includes one detail that matters for land owners along the route. Spring Hill's interconnection includes about 23,600 feet of force main, and the agreement prohibits future connections or taps to that line.

The mayor has also described a second option. At the same breakfast, the Williamson Herald reported, Fitterer said the city was planning a new system that could hold up to 700,000 gallons. The city's January statement on the moratorium included his commitment to "near term additional water reclamation capacity through public delivery of decentralized systems, interlocal agreements, or both." The Columbia link is the one of those that both city councils have now voted on.

The allocations and development review timelines

The Group 1 projects, especially June Lake and Legacy Pointe, account for most of the remaining development-agreement capacity.

Section 1 sets October 6, 2025, the date Resolution 25-238 was adopted, as the tolling date for development review timelines and vested-rights protections under Tennessee Code Annotated § 13-4-310.

Questions about the moratorium

Who declared the moratorium, the city or the state? Ordinance 25-29 states that the city declared it under Tennessee law to comply with TDEC Consent Order WPC2025-0093.

When does the Columbia connection open? The October 19 resolution lets the plan proceed, and the agreement ties service to TDEC's written approval and to completion of Columbia's new plant, which is expected in 2027.

Where can I read the allocations myself? They are in Section 2 of Ordinance 25-29, in the January 5, 2026 Board of Mayor and Aldermen agenda packet.

Greg Sanford has worked on Williamson County entitlement and land questions from both the commission side and the brokerage side. Request a private consultation.

WORK WITH GREG

Providing clients with ultimate bespoke representation, customized marketing strategy, and white-glove service. Excelling in exceeding expectations for buyers, sellers, and beyond.

Follow Me on Instagram